Haveli Bahadur Shah power plant successfully started 1230 MW combined cycle commercial operation
Inauguration of simple cycle operation (760 MW) of 1230 MW Haveli Bahadur Shah Jhang R-LNG Combined-Cycle Power Plant by Prime Minister of Pakistan,Mian Muhammad Nawaz Sharif.
First fire achieved for Gas Turbine #2 in a record 73 days from GT’s arrival at site.
Operations and Maintenance Agreement signed with Sepcolll Electric Power Construction Corporation.
First fire achieved for Gas Turbine #1 in 94 days from GT’s arrival at site.
Bid results announced for Operations & Maintenance Agreement.
Gas Turbine #2 laid on foundation.
Gas Turbine #2 arrived at facility.
Gas Turbine #1 laid on foundation.
Gas Turbine #1 arrived at facility.
Gas Supply Agreement signed with Sui Northern Gas Pipeline Limited (SNGPL).
Long Term Service Agreement (LTSA) signed with General Electric.
Ground Breaking of 1230 MW Haveli Bahadur Shah Jhang R-LNG Combined-Cycle Power Plant by Prime Minister of Pakistan, Mian Muhammad Nawaz Sharif.
Engineering, Procurement, and Construction (EPC) contract awarded to Power China.
Ground Breaking of 1230 MW Haveli Bahadur Shah Jhang R-LNG Combined-Cycle Power Plant by Prime Minister of Pakistan, Mian Muhammad Nawaz Sharif.