Balloki power plant successfully started 1223 MW combined cycle commercial operation
First fire achieved for Gas Turbine #2 in a record 64 days from GT’s arrival at site.
First fire achieved for Gas Turbine #1 in 66 days from GT’s arrival at site.
Operations and Maintenance Agreement signed with TNB REMACO, Malaysia.
Gas Turbine #1 delivered on site.
Steam Turbine arrived at facility.
Bid results announced for Operations & Maintenance Agreement.
Power Purchase Agreement signed with Central Power Purchasing Agency (Guarantee) Limited.
Gas Supply Agreement signed with Sui Northern Gas Pipeline Limited (SNGPL).
Long Term Service Agreement (LTSA) signed with General Electric.
Ground Breaking of 1223 MW Balloki, Kasur R-LNG Combined-Cycle Power Plant by Prime Minister of Pakistan, Mian Muhammad Nawaz Sharif.
Engineering, Procurement, and Construction (EPC) contract awarded to Harbin Electric International.